COMPLETED OBJECTS

ELECTRICAL DESIGN




Heading photo

COMPLETED OBJECTS

SOLAR POWER PLANTS OF ZAKARPATIA

The solar power plant is intended for industrial production of electricity by converting solar energy into environmentally friendly electrical energy in solar photovoltaic modules with its subsequent transformation into external electrical networks of the Zakarpattia region.

The goal of this project is the decentralization of the energy sector of Ukraine.

●  The designed stations occupy areas with a total area of ​​over 50 hectares;
● The projected estimated capacity of the stations in total is over 20,000 kW;
● The projected estimated average annual electricity generation is over 24,000 MW/h/year.

The Svitovyr company developed various sections of the projects. With an individual approach to each solar power plant in accordance with the requirements of the Customer and the technical conditions for connection issued by PJSC "Zakarpattiaoblenergo".

Heading photo

COMPLETED OBJECTS

SOLAR POWER PLANTS IN LVIV REGION

Svitovyr actively participated in the development of projects in full or in part of the projects of the following stations in the Lviv region:
- Photovoltaic solar power plant "Nahirne-1";
- Photovoltaic ground-based solar power plant "Nahirne-2";
- Solar power plant in the village of Kulykiv, Zhovkiv district, Lviv region; - Photovoltaic ground-based solar power plant "Shchyrets-1";
- Photovoltaic ground-based solar power plant "Shchyrets-2" (stages I and II); - Photovoltaic ground-based solar power plant FES "Semenivka"; - SOLAR POWER PLANT-1 in the village of Dobrivlany, Stryi district, Lviv region;
- SOLAR POWER PLANT-2 in the village of Dobrivlany, Stryi district, Lviv region;
- SOLAR POWER PLANT-3 in the village of Dobrivlyany, Stryi district, Lviv region.

Heading photo

COMPLETED OBJECTS

SOLAR POWER PLANTS OF THE CARPATHIAN REGION

The solar power plant is intended for industrial production of electricity by converting solar energy into environmentally friendly electrical energy in solar photovoltaic modules with its subsequent transformation into external electrical networks of the Precarpathian region.

General description of the plant:
- the designed plant is located on a plot of 4.98 hectares;
- the projected estimated capacity of the plant is 2494.8 kW;
- the projected estimated average annual electricity generation is 2703 MW/h/year.

The project provides for the following stages of construction of the solar power plant "New construction of a 2000 kW solar power plant in the "Hora" tract of the village of Myshyn, Kolomyia district, Ivano-Frankivsk region":
Installation of metering at the Myshyn solar power plant
Construction of 10 kV distribution networks.
0.4 kV networks.
Design of consumers of the solar power plant's own needs.
DC networks.
Automation and control system.

Heading photo

COMPLETED OBJECTS

INSTALLATION OF DISCONNECTOR ON 220 KV HV PSU

The project was developed for DTEK BURSHTYNSKA TPP (as part of the program “Change of the connection scheme of SSh-1A 220 kV to SSh-1B 220 kV”).

A number of tasks were completed:
● execution of project documentation
● dismantling of the 220 kV disconnector
● installation of the 220 kV disconnector
● performance of commissioning works.

Heading photo

COMPLETED OBJECTS

IMPLEMENTATION OF A SINGLE-PHASE FLASH PROTECTION SYSTEM

Implementation of a protection system against single-phase ground faults in 6 kV networks of VP 5 block DTEK Burshtynskaya TPP (using “ALTRA” devices).

A number of works performed within the framework of the project:
- execution of design documentation
- installation of a protection system (ALTRA devices)
- organization of a data transmission network
- performance of commissioning works.

Heading photo

COMPLETED OBJECTS

REPLACEMENT OF 110 KV CIRCUIT BREAKER WITH GPP-110/35/6

The work was carried out at the KVPAT STEBNYTSKE MINING AND CHEMICAL ENTERPRISE "POLIMINERAL"

A number of works were performed:
● execution of design documentation
● dismantling of the 110 kV circuit breaker
● installation of the 110 kV SF6 circuit breaker 120-SFM-32B SFM-SFM-32B 32B (CG Power Systems), installation of busbars
● performance of commissioning works.